I don’t get it?
"SR20 wing production, for example, which required over 1,700 man-hours per wing in December has been reduced to under 600 man-hours
I am trying to picture 10 people working on a wing all at the same time for 40 hours per week. At 1,700 hours it would take 4.25 MONTHS to make ONE wing. (Can’t imagine 10 people, seems they would be bumping into each other.) At a cost of $15.00/hr including benefits, that would be $51,000 for both wings not including materials. I can’t imagine it taking 4.25 months to make a wing.
600 hours is much more resonable, but to drop it by 65% in two months? I must be missing something?
10 people at 40hrs per week = 400 hrs per week
1700/400 - 4.1 - five weeks.
new way = 1.5 weeks
Dean
I have no idea how many people work on a wing at a time and have no idea what the hourly rate including benefits is.
I was mostly commenting on the number of hours stated to produce a wing.
Don’t want to start any rumors here!!
I meant weeks…was talking on the phone at the same time. Also note, I have no idea how many people work on a wing at a time. I also thought that was per wing, 2 per plane?
David
10 people at 40hrs per week = 400 hrs per week
1700/400 - 4.1 - five weeks.
new way = 1.5 weeks
Dean
It’s uni-wing construction - made the same mistake myself a few threads down.
I meant weeks…was talking on the phone at the same time. Also note, I have no idea how many people work on a wing at a time. I also thought that was per wing, 2 per plane?
David
10 people at 40hrs per week = 400 hrs per week
1700/400 - 4.1 - five weeks.
new way = 1.5 weeks
Dean
Regardless, the 1,700
hour number is
astonishing. Even
complex homebuilts only
take in the 3,000 -3,500
hr. range. My guess is they meant
to say 700 hours, but I
could easily be wrong.
I have 3 big concerns about the 1,700 number:
1)If it took 4 weeks per
wing, then to produce 5
planes a week would
entail 20 crews, each
devoting 1,700 hrs. per
wing to reach this goal.
2) Now, if they did manage
to reduce the manhours
by 1,100 per wing
without a change in
tooling, then I would be
a little concerned about
the quality.
3) If you look at
profitability and make
asumption sthat the cost of the plane is 50%
labor and 50% materials
and assume the
ENTIRE plane only
took 3,500 hours to
build (just over 2x the
total time for just the
wing) at a labor cost of
$30 per hour including
benefits, then the labor
component is $105,000
and the material cost is
$105,000. They would
be loosing money on
each plane and the more they produced the more they would loose!
I didn't even add in the
corporate overhead,
sales expense fixed
costs, (building, debt
service, insurance,
utilities). Ouch.
Well, based on Ian's last e-mail, they seem to be
getting their act
together and the
production rates are
onece agin going up.
Hopefully I will hear in
the next couple of
weeks about a delivery
date for SR22 s/n 17.
Paul, until then, how's it going? I need more SR22 trivia to keep living vicariously!
Marty
Regardless, the 1,700
hour number is astonishing. Even
complex homebuilts only take in the 3,000 -3,500 > hr. range. My guess is they meant
to say 700 hours, but I could easily be wrong.
well, even if they did cut 1,100 hrs from the procudtion time of the wing, the means they are saving about $30,000 per plane. That is great news for everyone. Who ever figured that out deserves one heck of a bonus!